Customer Name |
Production Park |
Location |
South Kirkby, West Yorkshire |
Building Use |
Rehearsal Space |
Size of Building / Construction |
17,000 sq. ft. – 20m high Older building – Lots of Glass |
Heaters |
1 Winterwarm / Warmco XR60 suspended, warm air heater |
Fuel Supply |
Natural Gas |
Ancillary Equipment |
9 large CECx Calecon 650 de-stratification fansDB8 Control Panel |
As part of a previous expansion, Production Park, a previous Warmco customer, had moved into this new specialist rehearsal space, which had no heating. Warmco were asked to install a Winterwarm / Warmco XR60, suspended, warm air heater and de-stratification fans in the space, to provide background heating to keep the practising acts warm.
To install the warm-air space heater and nine de-stratification fans so high up, between the lighting rigs, we hired in a specialist scissor platform to reach the roof structure. As this was a very high building at 20metres, de-stratification fans were essential to prevent heat accumulating in the highest reaches of the building. They will effectively re-distribute the heat through lower parts of the premises efficiently. This installation project was completed in four days, to create the minimum disruption to our customer.